Unimark EC3000 Series Especificações Página 17

  • Descarregar
  • Adicionar aos meus manuais
  • Imprimir
  • Página
    / 278
  • Índice
  • MARCADORES
  • Avaliado. / 5. Com base em avaliações de clientes
Vista de página 16
AIMS System and Services Agreement Page 17 of 60
6.2.9 Payment will be made to Contractor at:
Chris Keller
Air-Transport IT Services, Inc.
5950 Hazeltine National Drive
Orlando, FL 32822
Facsimile: 407-370-4657
ARTICLE 7
NOTICE TO PROCEED; LIQUIDATED DAMAGES
7.1 Notice to Proceed. Prior to beginning the performance of this System
Agreement, Contractor must receive an Initial NTP from the Contract
Administrator. Prior to beginning each phase of Services in the Statement of
Work, and prior to beginning any phase or task in a Work Authorization,
Contractor must also receive a Notice to Proceed from the Contract
Administrator.
7.2 Initial Notice to Proceed ("Initial NTP"). Prior to the execution of this System
Agreement, Contractor shall provide County with a properly completed Insurance
Certificate, the completion of, and submittal of, which is considered a condition
precedent to the execution of this System Agreement. County shall not issue the
Initial NTP until Contractor has complied with the requirements of this Section
7.2.
7.3 Completion of System Timetable/Liquidated Damages. Contractor shall
complete the System (including Services under such Work Authorizations as may
be issued pursuant to Article 9 hereof), through Final Acceptance, within twenty-
four (24) months from the date of the issuance of the Initial NTP ("Completion
Date"). If Contractor is unable to complete the System (including Services under
such Work Authorizations as may be issued hereunder), including Final
Acceptance, County shall have the option to terminate the Agreement and
Contractor shall then refund all monies received from County. Alternatively,
County is entitled to liquidated damages of Five Hundred Dollars ($500.00) per
day for each calendar day following the Completion Date, up to the date of Final
Acceptance. The Contract Administrator shall have the option to extend the
completion time period prior to the commencement of liquidated damages for
good cause shown, including without limitation a Force Majeure Event as
described in Section 20.21 or delay caused by the County. In the event of any
termination hereunder the Contractor shall not be required to a refund any
monies for or Goods, Hardware, or Software subsystems that were purchased by
the County from Contractor and retained by County after the termination of the
Agreement.
Exhibit 3
Page 17 of 278
Vista de página 16
1 2 ... 12 13 14 15 16 17 18 19 20 21 22 ... 277 278

Comentários a estes Manuais

Sem comentários