AIMS System and Services Agreement Page 31 of 60
the value of the change order or the calculated value of the time extension. All
change orders with a value of Two Hundred Fifty Thousand Dollars
($250,000.00) or more shall be approved in advance by the Board of County
Commissioners. All change orders with a value of less than Two Hundred Fifty
Thousand Dollars ($250,000.00) must be approved in advance by the Director of
Aviation.
16.3 Change orders and additional Services shall be at the rates and costs set forth
on Exhibits D and E. When both additions and decreases are involved in any
one change order, the combined effect shall be figured on the basis of the net
change in the compensation, if any.
16.4 Contractor shall not start work on any changes requiring an increase in the
compensation or the Contract time until a change order setting forth the
adjustments is approved and issued by the County. Upon receipt of a change
order, Contractor shall promptly proceed with the work set forth within the
document.
16.5 In the event satisfactory adjustment cannot be reached for any item requiring a
change in the compensation or Contract time, and a change order has not been
issued, County reserves the right at its sole option to either terminate the
Agreement as it applies to the items in question and make such arrangements as
may be deemed necessary to complete the disputed work, or submit the matter
in dispute to Consultant as set forth in Article 13 of this Agreement. During the
pendency of the dispute, and upon receipt of a change order, Contractor shall
promptly proceed with the change in the work involved and advise the Consultant
and Contract Administrator in writing within five (5) calendar days of Contractor's
agreement or disagreement with the method, if any, provided in the change order
for determining the proposed adjustment in the compensation or Contract time.
16.6 To avoid delays to completion of the Statement of Work and to mitigate damages
to the parties, change orders may be issued unilaterally by County, under
circumstances determined necessary by the Contract Administrator.
16.7 Value of Change Order Work. The value of any work covered by a change
order or of any claim for an increase or decrease in the Contract price shall be
determined in one of the following ways:
16.7.1 Unit Price. Where the work involved is covered by rates and costs in
Exhibits D and E, by application of such rates and costs.
16.7.2 Lump Sum. By mutual acceptance of a lump sum which Contractor and
County acknowledge contains a component for overhead and profit.
Whenever a change in the work is to be based on mutual acceptance of
a lump sum, whether the amount is an addition, credit or no change-in-
Exhibit 3
Page 31 of 278